Herat-Maymaneh
|
Ministry of Road and Transportation
|
Asas Rah
|
Jan 06
|
Apr 07
|
100%
|
|
completion work for Tombak Ring Way Lot#2
|
Pars Special Economic Energy Zone Co. Assaloyeh
|
ARDAM
|
May 03
|
Jun 07
|
100%
|
|
Reconstruction of Heart Airport
|
Es-Ko
|
--
|
Oct 05
|
Dec 06
|
100%
|
|
Flood Control Channel Pakage 1
|
Pars Special Economic Energy Zone Co. Assaloyeh
|
Bandab
|
Mar 05
|
Jun 06
|
100%
|
|
Herat/Maymaneh Bridges
|
Ministry of Road and Transportation
|
Asas Rah
|
Sep 05
|
Dec 06
|
100%
|
|
Site prepration for Ammonia, Urea phase #2
|
Petrochemical Industries Development
|
Petrochemical Development
|
Jan 04
|
Jan 05
|
100%
|
|
Chaghalvandy Khorram Abad High way
|
Ministry of Road and Transport
|
Mosha Rah
|
Apr 02
|
Dec 03
|
100%
|
|
Tombak Ring Way Lot #2
|
Pars Special Economic Energy Zone Co. Assalouyeh
|
ARDAM
|
May 03
|
Dec 05
|
100%
|
|
Petrochemical Flare Passive Culvert
|
Petrochemical Industries Development Management Co.
|
Mandrow/ Naghshe Jahan
|
Apr 03
|
Dec 04
|
100%
|
|
Temporary Facilities for Phases 6, 7 & 8 South Pars Gas Field Development
|
Toyo Engineering Co. (Joint Venture of TEC/IDRO/JGC/DIC)
|
TEC/IDRO/ JGC/DIC
|
Jan 03
|
Oct 04
|
100%
|
|
Road Crossing Culvert Phases 6, 7 & 8 South Pars Gas Field Development
|
Toyo Engineering Co. (Joint Venture of TEC/IDRO/JGC/DIC)
|
TEC/IDRO/ JGC/DIC
|
Dec 03
|
Jul 04
|
100%
|
|
Civil Work (C5 Package) Phases 6, 7 & 8 South Pars Gas Field Development
|
Toyo Engineering Co. (Joint Venture of TEC/IDRO/JGC/DIC)
|
TEC/IDRO/ JGC/DIC
|
Mar 04
|
Apr 07
|
100%
|
|
Civil Work (C4B Package 3) Phases 6, 7 & 8 South Pars Gas Field Development
|
Toyo Engineering Co. (Joint Venture of TEC/IDRO/JGC/DIC)
|
TEC/IDRO/ JGC/DIC
|
Apr 04
|
Apr 07
|
100%
|
|
Harat/ Maymaneh (Afghanestan) Main Road
|
Ministry of Road & Transportation
|
Asas Rah
|
Jul 04
|
Dec 06
|
100%
|
|
Khorram Abad/ Boroojerd Main Road Lot #1G
|
Ministry of Road & Transportation
|
Moshara
|
Jul 04
|
Dec 04
|
100%
|
|
Khorram Abad Ring Way
|
Ministry of Road and Transport
|
Haraz Rah
|
Jan 89
|
Jan 96
|
100%
|
|
Khorram Abad Air port
|
Civil Aviation
|
Foroud Rah
|
Feb 93
|
May 98
|
100%
|
|
Khorram Abad Interchange
|
Ministry of Road and Transport
|
Haraz Rah
|
May 97
|
Oct 99
|
100%
|
|
Reconstruction of Khorran Abad / Tehran
|
Ministry of Road and Transport
|
Mosha Rah
|
Jun 98
|
Oct 01
|
100%
|
|
Part one of Chaghalvandy/Boroujerd High way
|
Ministry of Road and Transport
|
Mosha Rah
|
Aug 97
|
Feb 02
|
100%
|
|
Concrete Production for South Pars Gas Field Development Phase 1
|
Ministry of Oil
|
Iran Development Reconstruction
|
Aug 00
|
Feb 02
|
100%
|
|
Slope Protection of Borzouyeh Petrochemical
|
Borzouyeh Petrochemical Co.
|
Iran Ark
|
Jan 02
|
Sep 02
|
100%
|
|
Khorram Abad-Andimeshk Ring Way
|
Ministry of Road and Transport
|
Haraz Rah
|
Jan 99
|
Aug 99
|
100%
|
|
Site Clearance & Landscaping Nakh Tire Factory
|
Ministry of Industries
|
Sazeh
|
Jan 99
|
Jun 99
|
100%
|
|
Assalouyeh Ring Way Part A, 2A & 2B
|
Pars Special Economic Energy Zone Co. Assalouyeh
|
Faradid
|
Jun 01
|
Aug 03
|
100%
|
|
Khorram Abad-Chaghalvandi Road
|
Ministry of Road and Transport
|
Mosha Rah
|
Mar 02
|
Nov 03
|
100%
|
|
Civil construction Phases 4 & 5 South Pars Gas Development Assalouyeh
|
Hyundai Engineering & Construction Co.
|
Hyundai
|
Aug 02
|
Jun 03
|
100%
|
|
Equipment Foundation & Pipe Rack Phases 4 & 5 South Pars Gas Field Development / Assalouyeh
|
Hyundai Engineering & Construction Co.
|
Hyundai
|
Nov 02
|
Dec 03
|
100%
|
|
Site Preparation & Concrete Flood Channel- Phases 6,7 & 8 South Pars Gas Field Development / Assalouyeh
|
Petropars Ltd.
|
EIC
|
Feb 03
|
Dec 03
|
100%
|
|
Site Preparation for Foreigner Camp & Desalination Plant Phases 6, 7 & 8 South Pars Gas Field Development
|
Toyo Engineering Co. (Joint Venture of TEC/IDRO/JGC/DIC)
|
TEC/IDRO/ JEC/DIC
|
Nov 03
|
Feb 04
|
100%
|
|
Cutting Work of Condensate Tank Area Phases 6, 7 & 8 South Pars Gas Field Development
|
Toyo Engineering Co. (Joint Venture of TEC/IDRO/JGC/DIC)
|
TEC/IDRO/ JEC/DIC
|
Nov 03
|
Mar 04
|
100%
|
| Name of Contract | Client | Supervisor | Award Date |
Percentage of work completed
|
|
Rehabilation of Herat-Turghandi Main Road
|
Ministry of Road and Transportation
|
Ministry of Public Works
|
Mar 07
|
10%
|
|
Rail Road Sangan-herat
|
Ministry of Road and Transportation
|
Iran Eston
|
Jan 07
|
35%
|
|
Asphalt Coating Arak-Salafchegan Main Road
|
Ministry of Road and Transportation
|
HarazRah
|
Apr 07
|
7%
|
|
Box Culvert South Pars Gas Field Development
|
P.O.G.C.
|
P.O.G.C.
|
Apr 07
|
2%
|
|
Land Scaping
|
Mobin Petrochemical Co.
|
Sazeh
|
Apr 06
|
85%
|
|
Dorood-AliGodarz Main Road
|
Ministry of Road and Transportation
|
Imen Rah
|
Jul 06
|
20%
|
|
None Industrial Buildings
|
Ghadir Urea & Amonia Petrochemical Co.
|
Gadir
|
Jan 06
|
90%
|
|
Manholes-Catch Basin & Valve Pits works phases 9-10
|
Oil Industries Engineering and Construction(OIEC)
|
OIEC
|
Jul 05
|
95%
|
|
Firooz Abad/ Jam Main Road
|
Ministry of Road & Transportation
|
Faradid
|
Jun 04
|
99%
|